I'd like to tell you about my framework design. In order to the frame house was strong, and the cost of its construction was minimal, the spans in the rooms must not be longer than the construction of timber (logs or planks), taking into account the thickness of walls. Since the length of a standard board is 6 m., a wall thickness is 170mm, a width is 5,4 - 5,6 m. Based on these requirements, we had to make a load-bearing wall in the middle of the house and move it about the center of house, based on its ceiling beams. A construction of frame. The frame homes can be built by several ways, we have chosen in our view the simplest, most cost-effective and acceptable way for us to build.
First, we make a bottom ledge from the boards 150 x 50 mm. laid on the edge of the finished foundation of home, in our case the pillar. Inside boards of the lower trim are connected to each other at the corners with screws (100-120mm.). The boards are fastened with screws (95 mm.), and then the outside boards.
After the lower trim boards are connected by screws, you should align the upper part of boards by a power planer, check the level, a diagonal and the corners of the bottom frame. Mark the location of the floor lag, make the grooves with a keyhole saw in the internal boards and secure the floor joists to the posts of the basement and the lower ledge.Timbers with a section of 50 x 50 mm, which will be supported on the ends of floor boards you should consolidate around the perimeter to the inside board of the ledge. Pull together, boards with nails of the ledge, using the nails of 200 and 150 mm, staggered at intervals of 50 – 80 cm. During the construction of frame houses, a first thing to do is the floor and then the erection of walls, but as the weather was rainy, we had to change a technology, not to wet the floor boards. In the beginning we had to make walls.
The installation of the OSB we began with the angle secured to the frame corner posts two sheets of OSB we got a base angle from which the sheets were fastened in a circle leaving openings for the windows. With this method of installation of walls we do not need to install the rack holding the frame in the upright position, in the future it will be nothing more than a waste of material, and problems with the installation of insulation in the walls. We made a roof sheathing on the rafters the board 25 x 125 mm at intervals of 8 cm between the boards. We cut the sheathing boards leaving issues over the gables of 30cm. We laid a ruberoid and roofing sheets of onduline. We laid three layers of insulation between the ceiling joists, insulation plates were covered with vellum sheets and closed with OSB on the other side of the house. Once the frame house was covered with a roof and the rain could not stop us to produce the work inside the home. We removed a temporary backup of a large span roof, floor boards were turned face up, they were rallied together and attached to lags with screws into the groove.